Due to a shift in the construction schedule, the Galestown Road detour, which began on May 18 will now last until July 21. This will give the contractor adequate time to finish the paving, install safety features, and receive final inspection.
As you know, we recently started construction on the North Site. We are installing stormwater management control, clearing and grading the site, and making improvements to Galestown Rd.
We are coordinating the upcoming detour with NCDOT, Richmond County, emergency services, law enforcement, schools and the community.
Please do not hesitate to contact our Community Line at (980) 296-1919 or if you have any questions or concerns. Project updates will be posted to www.VulcanRockinghamQuarry.com.